12. pants
Spēkā · redakcija pārbaudīta 2026-05-17
The NEA, through the BCH Task
Force will also account to UNEP for the use of funds by providing
the following upon completion of the procurement activities:
a. A complete inventory of
equipment purchased with invoice details and confirmation that
insurance contracts and guaranties are in place (use BCH Form 6
in Handbook).
b. Proof of BCH setup
functionality, by providing the results of a test BCH
communication (use BCH Form 7 in Handbook).
c. At the end of the Project a
Request for Transfer of Equipment will be submitted to the
UNEP-GEF BCH project management for approval, to ensure the
sustainability of the equipment and service, taking into
consideration the maintenance costs and the obligations of the
recipient institution(s) for the equipment.